Assessment Summary
0 of 175 Questions completed
Questions:
Information
You have already completed the assessment before. Hence you can not start it again.
Assessment is loading…
You must sign in or sign up to start the assessment.
You must first complete the following:
Results
Results
0 of 175 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- 32
- 33
- 34
- 35
- 36
- 37
- 38
- 39
- 40
- 41
- 42
- 43
- 44
- 45
- 46
- 47
- 48
- 49
- 50
- 51
- 52
- 53
- 54
- 55
- 56
- 57
- 58
- 59
- 60
- 61
- 62
- 63
- 64
- 65
- 66
- 67
- 68
- 69
- 70
- 71
- 72
- 73
- 74
- 75
- 76
- 77
- 78
- 79
- 80
- 81
- 82
- 83
- 84
- 85
- 86
- 87
- 88
- 89
- 90
- 91
- 92
- 93
- 94
- 95
- 96
- 97
- 98
- 99
- 100
- 101
- 102
- 103
- 104
- 105
- 106
- 107
- 108
- 109
- 110
- 111
- 112
- 113
- 114
- 115
- 116
- 117
- 118
- 119
- 120
- 121
- 122
- 123
- 124
- 125
- 126
- 127
- 128
- 129
- 130
- 131
- 132
- 133
- 134
- 135
- 136
- 137
- 138
- 139
- 140
- 141
- 142
- 143
- 144
- 145
- 146
- 147
- 148
- 149
- 150
- 151
- 152
- 153
- 154
- 155
- 156
- 157
- 158
- 159
- 160
- 161
- 162
- 163
- 164
- 165
- 166
- 167
- 168
- 169
- 170
- 171
- 172
- 173
- 174
- 175
- Current
- Review
- Answered
- Correct
- Incorrect
-
Question 1 of 175
1. Question
1. A project manager is planning the next release for an ICT project. The project team has completed two releases to date, and the product backlog for the next release has been confirmed. Which of the following tools should the project manager use to plan the duration for the next release?
CorrectIncorrect -
Question 2 of 175
2. Question
2. A customer is upset because a critical issue for a project deliverable has not been resolved by the agile team, even though troubleshooting has been running for several weeks. During the daily meetings, the team complains about the technical challenge and their lack of knowledge to resolve the issue. Which two actions should the project manager take to resolve this situation? (Choose two)
CorrectIncorrect -
Question 3 of 175
3. Question
3.A key member of an agile team was replaced with a less experienced member. One of the stakeholders is concerned that the project will not be delivered on time because of the new team member. What should the project manager do to ensure successful project delivery?
CorrectIncorrect -
Question 4 of 175
4. Question
4. In order to function optimally, a project team should have a project charter that states the purpose of the project and a business case for the project among other high-level information.Which question should the project charter answer?
CorrectIncorrect -
Question 5 of 175
5. Question
5. A project manager walked into a project office and found a team member and a supplier representative engaged in a disagreement over a clause in the supply agreement. The project manager invites the supplier for a negotiation with the project team to resolve the conflict. Applying the principles of negotiation, for what should the project manager and team aim?
CorrectIncorrect -
Question 6 of 175
6. Question
6. During a phase at project execution, a quote for the required services was requested from a vendor, and the work was estimated at $200,000. As the project progressed, requirements were updated following the company’s procurement process, and a modified quote was received for more than $350,000. The allocated contingency funds are not sufficient to cover the difference. What should the project manager do?
CorrectIncorrect -
Question 7 of 175
7. Question
7. A company delivers technical services to customers using external labor including hiring specialized personnel to reduce costs by delivering an in-house service. Some of the stakeholders are frustrated that the resources are taking too much time to deliver the service. The company has just recruited a new project manager to help address these stockholders concerns. What should the project manager do?
CorrectIncorrect -
Question 8 of 175
8. Question
8. A project manager is managing an integrated project involving both hardware and software development and the development team proposes to use agile methodologies for development. What should the project manager do?
CorrectIncorrect -
Question 9 of 175
9. Question
9. A project manager is contracted to manage a project for a startup with grants from a foreign source. Midway into this project, the project manager is informed that there is a government regulatory requirement that might affect the project because the customer has foreign funding sources. What should the project manager do since all the necessary approvals for this project have been received?
CorrectIncorrect -
Question 10 of 175
10. Question
10. A compliance issue was found during the course of a project. This caused an inspection of the product by the internal audit team. As a result, the project fell behind schedule. What should the project manager have done initially to avoid this issue?
CorrectIncorrect -
Question 11 of 175
11. Question
11. An agile project is in its first of ten iterations. After the iteration review, the team receives stakeholder feedback that the first deliverable is not aligned with the project objectives. What should the project manager do?
CorrectIncorrect -
Question 12 of 175
12. Question
12. During project closure, the project sponsor requests that a deliverable, developed by a contractor, be transferred to a nonprofit organization at no cost. The procurement documentation states that ownership of the deliverable reverts to the contractor once the procurement contract is finished. What should the project manager do?
CorrectIncorrect -
Question 13 of 175
13. Question
13. A project manager is managing multidisciplinary teams. During the last project review meeting, the project manager realized that there is friction between some of the team members. What should the project manager do next?
CorrectIncorrect -
Question 14 of 175
14. Question
14. A project manager is planning for a complex project that must deliver a high-quality product within the agreed-upon budget. The project stakeholders are eager to see the product launched and are pressuring the team to deliver the product as soon as possible. The project manager must determine the project’s estimated duration and address stakeholder expectations. How should the project manager determine a realistic project duration estimate?
CorrectIncorrect -
Question 15 of 175
15. Question
15. A project team member continues to change a colleague’s deliverable during every sprint. The colleague has asked the project manager to intervene. What action should the project manager take to address the concern?
CorrectIncorrect -
Question 16 of 175
16. Question
16. A project manager recently took over a project from a project manager who left the company. The new project manager is aware that the previous project manager had a very authoritarian style of management and made all the decisions regarding the project. The new project manager notices that a senior supervisor’s morale is low.
What should the new project manager do?
CorrectIncorrect -
Question 17 of 175
17. Question
17. During the final sprint review, the product owner stated that the product does not deliver any value. The project manager believes that the product meets all the provided specifications. The team is confused by the product owner’s statement.
What should the project manager do when using a hybrid approach?
CorrectIncorrect -
Question 18 of 175
18. Question
18. At the start of a project, the team chose to leverage an agile approach to deliver the project, using user stories to capture requirements. As part of the organization’s control framework, the internal compliance department will request a copy of the approved requirements document.
What should be done to meet this compliance request?
CorrectIncorrect -
Question 19 of 175
19. Question
19. A company has been using predictive methods for a very long time and is trying to implement a few iterative initiatives within its project framework. A project manager has been appointed to lead the first project in this hybrid environment.
How should the project manager build awareness of the hybrid approach within the organization?
CorrectIncorrect -
Question 20 of 175
20. Question
20. A Scrum team is halfway to its release. During the sprint demo, new software is selected by one of the developers and presented to the team. The new software was not planned work but meets the date for the release. Several prioritized features for the next two sprints are disrupted.
What actions should the team do to minimize the disruption?
CorrectIncorrect -
Question 21 of 175
21. Question
21. A project team is working on backlog items within a four-week sprint. Suddenly, a critical team member announces that they will unexpectedly be absent for one week, leaving ongoing tasks incomplete.
What would be the most appropriate action for the project manager to take in this situation?
CorrectIncorrect -
Question 22 of 175
22. Question
22. A project manager is planning for a project team that will soon start work on a critical subsystem. There are two technical alternatives identified for the subsystem, but it is not clear if either alternative will perform satisfactorily. The project will be compromised if the performance of the critical subsystem falls short.
What should the project manager do first?
CorrectIncorrect -
Question 23 of 175
23. Question
23. A large transformation project that requires cross-functional effort from various business teams is in progress.
Which two actions should the project manager take first to complete the stakeholder register? (Choose two)
CorrectIncorrect -
Question 24 of 175
24. Question
24. An IT contract for a project states that all team members must be certified in IT security. The project manager discovers that one team member presented a fake certificate.
What should the project manager do first to handle this situation?
CorrectIncorrect -
Question 25 of 175
25. Question
25. Due to market changes, a company decided to speed up its product release schedule, moving from yearly cycles to quarterly cycles. The project manager views this as an excellent opportunity to use an agile life cycle, but upper management is not sold on the idea.
What should the project manager do to increase the chances of success by using this approach?
CorrectIncorrect -
Question 26 of 175
26. Question
26. A project team has just reached a project milestone successfully. The project manager noticed that the team performed extremely well.
Which approach should the project manager use to communicate with the team about their performance?
CorrectIncorrect -
Question 27 of 175
27. Question
27. Due to budgetary constraints, the program manager has requested that project managers prioritize resources over schedule milestones. A project manager reviews the resource histogram and finds that 80% of the project’s resources will be used in the last month of the project.
What should the project manager do?
CorrectIncorrect -
Question 28 of 175
28. Question
28. A project manager is managing an upgrade from an older system to a new version. Halfway through the upgrade, the older system failed to upgrade and could not be restored.
What should the project manager do to manage this situation?
CorrectIncorrect -
Question 29 of 175
29. Question
29. A project manager is working on a project that has been ongoing for some time and is currently at the 70% completion mark. The development team has been diligently following the project management plan and scope defined in the project charter. During a product review meeting, a stakeholder complains that additional features should be included. These features were not initially part of the project scope but have now become a pressing concern for the stakeholder.
What should the project manager do next?
CorrectIncorrect -
Question 30 of 175
30. Question
30. A project manager is assigned to a project that is transitioning the organization to adopt agile principles. The project scope definition is in progress, but the project team wants to have a less formal definition.
What should the project manager do first?
CorrectIncorrect -
Question 31 of 175
31. Question
31. A project manager observed that a team member is becoming increasingly disengaged from an ongoing project. What should the project manager do to help ensure participation from this team member?
CorrectIncorrect -
Question 32 of 175
32. Question
32. An inexperienced project manager requires HR support for a project. The HR manager hired interns and sent them for training. However, the training did not deliver on the competency-based outcomes. The HR manager is not willing to accept the training costs because the training budget is exhausted.
What should the project manager do to resolve the situation?
CorrectIncorrect -
Question 33 of 175
33. Question
33. A project manager wants to ensure that virtual team meetings are effective. What should the project manager do?
CorrectIncorrect -
Question 34 of 175
34. Question
34. The project manager is responsible for a major project that involves working with many vendors. A key project concern is related to the quality and timely delivery of procured products and services as committed by the vendors.
What should the project manager do to ensure that the products meet the quality requirements and are delivered on time?
CorrectIncorrect -
Question 35 of 175
35. Question
35. An urban hotel design project has an international, multidisciplinary, and cross-cultural team. The project manager is in the process of developing the first version of the project management plan.
What should the project manager do?
CorrectIncorrect -
Question 36 of 175
36. Question
36. In a large organization, a project is experiencing communication difficulties. Team members and functional leaders are expressing that they are informed too late or not included in project discussions, or are simply unaware of important project delivery information.
How should the project manager address this situation?
CorrectIncorrect -
Question 37 of 175
37. Question
37. A project manager working with a culturally diverse team discovers major intra-team conflicts during project execution.
What should the project manager do?
CorrectIncorrect -
Question 38 of 175
38. Question
38. A project manager is leading a major product development project. The project is currently in the middle of the fifth sprint, and the product release is scheduled for next quarter. The project manager receives unexpected news that the company has just been formally acquired by a major competitor. This competitor already has a similar product in their portfolio.
What immediate action should the project manager take to address the situation effectively?
CorrectIncorrect -
Question 39 of 175
39. Question
39. A project manager is overseeing an agile project that has finalized scope and compliance requirements. During a regular project review, a stakeholder informs the project manager that proposed changes to the country’s safety legislation could impact the project’s scope.
What should the project manager do?
CorrectIncorrect -
Question 40 of 175
40. Question
40. An agile project is in its first of 12 iterations, and each iteration lasts two weeks. In the first iteration review, the stakeholders ask for monthly reports moving forward.
What should the project manager do?
CorrectIncorrect -
Question 41 of 175
41. Question
41. A project manager is assigned to an ongoing project with virtual team members from different countries who are working remotely in different time zones. The project manager notices that team members are not completing project activities on time and are unable to produce the expected deliverables due to irregular communications.
How should the project manager resolve this?
CorrectIncorrect -
Question 42 of 175
42. Question
42. A project team adopted agile practices to meet the business need to develop an application. One of the senior team members inconsistently attends the team meetings, even the daily standup meetings. This senior team member then asks other team members to provide status updates on the senior team member’s behalf.
What should the project manager do to handle this situation?
CorrectIncorrect -
Question 43 of 175
43. Question
43. A project manager works at a construction company. The current project is a three year, multimillion-dollar initiative to rebuild a stadium. The first phase of the project has been completed within the three month timeframe and within budget.
What should the project manager do next?
CorrectIncorrect -
Question 44 of 175
44. Question
44. During project execution, the audit team determined that critical regulatory requirements are not being met. What should the project manager have done first to avoid this problem?
CorrectIncorrect -
Question 45 of 175
45. Question
45. A project manager provided video-based training for new software but several team members reported feeling unprepared to use it.
What should the project manager have done to ensure effective training?
CorrectIncorrect -
Question 46 of 175
46. Question
46. One of the retrospective action items that has recurred for the past two iterations is related to the verification and validation of the delivered functionality before production readiness.
Which two solutions should the project manager use? (Choose two)
CorrectIncorrect -
Question 47 of 175
47. Question
47. In a company that recently adopted hybrid practices, a project is struggling to perform as expected. Neither the project manager nor the team members have previous experience with this new approach to project management. The project manager wants to ensure the transition to hybrid practices is pro?ducing the desired results.
What should the project manager do ?
CorrectIncorrect -
Question 48 of 175
48. Question
48. A project manager for a new project is tasked with applying agile practices to improve team performance. Which approach should the project manager take?
CorrectIncorrect -
Question 49 of 175
49. Question
49. The project manager discovers that a stakeholder provides inaccurate status reports to the steering committee. Moreover, the stakeholder does not have accurate information on the project.
What should the project manager do first?
CorrectIncorrect -
Question 50 of 175
50. Question
50. A project manager has been asked to manage an existing complex project. Some goals have already been delivered by the previous project manager. While reviewing the project management plan, the project manager realizes that one of the key deliverables is missing from the project goal.
What should the project manager do next to ensure the expected project value is delivered?
CorrectIncorrect -
Question 51 of 175
51. Question
51. A project manager is assigned to a project in a country where the company has not previously done business. At the beginning of the project, the project manager realizes that there are certain regulatory requirements for which the project team has no experience.
What should the project manager do next?
CorrectIncorrect -
Question 52 of 175
52. Question
52. A project team is in the planning phase of a complex project. The project has an end-date constraint to launch a new product with which they have no previous experience. The project sponsor is requesting a detailed schedule, but the team is unable to predict when tasks will occur throughout the project lifecycle, especially because some of them are dependent on deliverables by other business units.
What life cycle methodology should the project manager use in this situation?
CorrectIncorrect -
Question 53 of 175
53. Question
53. The development phase of a new product has concluded. The validation test is about to start, but the test lead disagrees with the criteria for the test. What should the project manager do?
CorrectIncorrect -
Question 54 of 175
54. Question
54. A project to develop a new software program has been delivered. The software has been put into production, but members of the project team are continuously contacted by users asking how to use or report problems, even though the project received administrative closure.
What should the project manager have done to prevent this situation?
CorrectIncorrect -
Question 55 of 175
55. Question
55. An agile team created a risk register for a project. All initial risks were identified using stakeholder interviews, workshops, and information from the project charter. What should the project manager do to manage the risk register and the associated risks for the remaining project duration?
CorrectIncorrect -
Question 56 of 175
56. Question
56. A project is in the execution phase when new team members are onboarded. Before onboarding the new team members, what should the project manager do to reduce the impact of this action on project performance?
CorrectIncorrect -
Question 57 of 175
57. Question
57. A company has started doing agile projects. The project sponsor is frustrated and does not understand the new requirements gathering process, which seems to be incomplete and moving too fast.
What should the project manager do?
CorrectIncorrect -
Question 58 of 175
58. Question
58. Production of a specific machine in a factory was contracted through a foreign supplier. Prior to delivery of the final two components, the supplier informs the project manager that they need to renegotiate prices or the components will not be delivered.
What should the project manager do first?
CorrectIncorrect -
Question 59 of 175
59. Question
59. A project manager is currently overseeing a hybrid project that has specific scope and quality requirements. However, due to recent changes in a competitor’s product, there is a growing concern that the project’s deliverables may become obsolete by the time the project is completed.
What should the project manager do to address the potential obsolescence of deliverables?
CorrectIncorrect -
Question 60 of 175
60. Question
60. A project manager has recently been assigned to an existing multinational project and is not familiar with the key stakeholders.
What should the project manager do?
CorrectIncorrect -
Question 61 of 175
61. Question
61. A complex, multimillion-dollar, multi-year product development project requiring unique knowledge is 70% complete. Contract termination is a possibility due to project deliverables and execution being not acceptable. Despite the strained relationship, the vendor is ready for rework at no penalty.
What should the project manager do to manage this situation?
CorrectIncorrect -
Question 62 of 175
62. Question
62. A project manager has a newly formed team that includes junior members who have not worked on agile projects before. The product owner wants to ensure that the team performs as expected in the sprint.
What should the project manager do?
CorrectIncorrect -
Question 63 of 175
63. Question
63. During the final stage of a project, one of the key stakeholders asks the project manager to brief the executive board about the return on investment (ROI) and any relevant new commercial value identified during project implementation.
What should the project manager do next?
CorrectIncorrect -
Question 64 of 175
64. Question
64. One of the project vendors is late in providing a related product solution, which is affecting the release due dates. What should the project manager do to help the agile team manage this impediment?
CorrectIncorrect -
Question 65 of 175
65. Question
65. In the midst of an ongoing agile construction project, the project manager receives notification that the local government has recently approved stricter sustainability legislation applying to all construction projects in the region. These new regulations will have an impact on the project’s materials and processes related to sustainability.
What should the project manager do first to adapt to these newly instituted environmental parameters?
CorrectIncorrect -
Question 66 of 175
66. Question
66. Before a project evaluation meeting, a key stakeholder complains that the project does not deliver the expected business benefits. The project manager needs to prepare for the meeting to effectively address the complaint.
What should the project manager do first?
CorrectIncorrect -
Question 67 of 175
67. Question
67. A project manager is reviewing the project status with the team and identifies that a vendor resource can be released earlier than planned. The project manager reviews the schedule, confirms this change, and informs the vendor. The vendor argues that the resource must stay for a certain period of time.
What should the project manager do?
CorrectIncorrect -
Question 68 of 175
68. Question
68. A team is working in a highly regulated industry and the compliance department keeps pushing documentation and process steps that interfere with the team’s desired way of working. Team frustration increases with the compliance department, and the team asks the project manager to intervene.
What approach should the project manager take?
CorrectIncorrect -
Question 69 of 175
69. Question
69. project team is installing a fiscal metering system for a crude oil terminal. The project manager has requested a metering system, conducted a factory acceptance test, and delivered meters to the terminal for installation. While onsite, local regulators participated in the factory acceptance tests and declined approvals for the meters due to a breach of statutory procedures. This led to delays in completing testing and had an overall impact on the project cost and schedule.
How could the project manager have prevented this situation?
CorrectIncorrect -
Question 70 of 175
70. Question
70. For quality assurance, a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were unavailable.
Why is an attendance list important?
CorrectIncorrect -
Question 71 of 175
71. Question
71. A project manager is appointed to design and develop a strategy for a government organization. The project manager recognizes that the project has a limited amount of detailed information to prepare project estimates. However, several other government organizations have already successfully adopted the same strategy.
In this scenario, which type of estimating method should the project manager select?
CorrectIncorrect -
Question 72 of 175
72. Question
72. An agile project team is building a website for a client. The client informs the product owner that their company has decided to release the website one month ahead of schedule, in order to take advantage of a business opportunity.
What should the project manager have the team do?
CorrectIncorrect -
Question 73 of 175
73. Question
73. During an iteration, the team spent twice as much time as expected because one of the product backlog items was complex and could not be split into smaller items.
What should the project manager do?
CorrectIncorrect -
Question 74 of 175
74. Question
74. A project manager is managing a construction project that is 40% through the execution phase. The project sponsor has asked the project manager to ensure that all key stakeholders are still committed to the project.
How should the project manager assess the stakeholders’ current engagement levels?
CorrectIncorrect -
Question 75 of 175
75. Question
75. An organization is halfway through a five year project and everything has progressed as scheduled. The latest project assessment indicates that the project will not be in compliance with a recently introduced international regulation.
What should the project manager do?
CorrectIncorrect -
Question 76 of 175
76. Question
76. A team member is scheduled to visit an overseas client site next week. However, the project manager overheard the team member tell a project coordinator that their functional manager denied the team member’s request for time off as compensation for the client visit. The project manager needs to ensure that the team member will visit the client site next week.
What should the project manager do?
CorrectIncorrect -
Question 77 of 175
77. Question
77. A director is acting as the product owner for a government software project. The director is repeatedly unable to engage with the team and provide regular and important feedback on project artifacts.
What should the project manager do to resolve this?
CorrectIncorrect -
Question 78 of 175
78. Question
78. A company is expanding, and the project manager is contemplating whether to hire new resources or outsource resources from an approved vendor team. What should the project manager focus on regarding this decision?
CorrectIncorrect -
Question 79 of 175
79. Question
79. A project manager is meeting with a critical third-party supplier that provides discounted services. During the meeting, the supplier complains that they are dissatisfied with their return on investment (ROI). What should the project manager do to resolve this situation and avoid putting the project at risk?
CorrectIncorrect -
Question 80 of 175
80. Question
80. A project manager has been informed that the first of several major deliveries from another country will be delayed. These deliveries are on the critical path, and the delay will result in a missed milestone.
What should the project manager do first?
CorrectIncorrect -
Question 81 of 175
81. Question
81. A team member raises a concern that some deliverables may not be compliant with certain regulations.
What should the project manager do?
CorrectIncorrect -
Question 82 of 175
82. Question
82. A project manager in a quickly growing hybrid organization is becoming increasingly frustrated at the rapid amount of change in daily operations. Several newer team members have already left the team or have been promoted to other roles in the organization.
What should the project manager do to ensure the project governance remains stable?
CorrectIncorrect -
Question 83 of 175
83. Question
83. A project manager is building a project team. All of the project team members have worked together on previous projects. One of the team members is known for challenging most organizational procedures and processes.
What should the project manager do first to ensure a smooth project initiation?
CorrectIncorrect -
Question 84 of 175
84. Question
84. A project manager noticed that one team member is frequently absent from project team meetings. Instead of working on the current project, the team member has been working on a task assigned by their functional manager.
What should the project manager do to resolve this issue?
CorrectIncorrect -
Question 85 of 175
85. Question
85. A conflict about how to proceed has developed between two team members prior to a release. The team needs to work together to complete the product release.
What should the project manager do first to defuse the situation?
CorrectIncorrect -
Question 86 of 175
86. Question
86. A company that has traditionally used predictive approaches has been experimenting with the use of agile in portions of a project. Because the company has been pleased with the results, the project sponsor now requests that the entire project be converted to agile.
What should the project manager do?
CorrectIncorrect -
Question 87 of 175
87. Question
87. A project manager decided that using an agile approach for a new project will deliver the best outcomes. Some of the team members were resistant to using agile techniques and decided to use predictive approaches to carry out their work.
What should the project manager have done at the beginning of the project?
CorrectIncorrect -
Question 88 of 175
88. Question
88. A vendor for a large and complex project has been performing more work than what was originally anticipated in the time and material contract. This type of contract caused the project to be behind schedule and over budget. The contract is about to expire.
What should the project manager do?CorrectIncorrect -
Question 89 of 175
89. Question
89. A project is about to begin and a new regulation has imposed a deadline that will adversely impact the project. Failing to comply with the regulation will result in hefty fines for the organization. The project is key to meeting the organization’s annual goals.
What should the project manager do first?
CorrectIncorrect -
Question 90 of 175
90. Question
90. A project manager is implementing a phase of an IT project in a location that is prone to security issues. A team member, working at a remote site, notifies the project manager that a permit fee was not received by the local regulatory agency involved; however, the project manager is certain that the fee was paid. The team member reminds the project manager that a test on the critical path is scheduled for that location on the same day.
What should the project manager do?
CorrectIncorrect -
Question 91 of 175
91. Question
91. A project manager works in an organization where the culture encourages virtual teams. New challenges arise periodically in this environment, and the project manager currently is in the early stages of a new agile project.
What should the project manager do to help the team overcome these challenges?
CorrectIncorrect -
Question 92 of 175
92. Question
92. A team is working on an innovation project using an incremental approach. After every status meeting, some key stakeholders complain that they have not been briefed to prepare for the meeting.
What should the project manager do to prevent this from occurring again?
CorrectIncorrect -
Question 93 of 175
93. Question
93. A project is challenged by a multitude of problems resulting in defects and stakeholder complaints. The project manager has been contemplating a quick and effective approach to address the problems.
Which two actions should the project manager take? (Choose two)
CorrectIncorrect -
Question 94 of 175
94. Question
94. A lengthy upgrade project is being delivered in a series of phased outputs. The end users will face some level of disruption during each phase prior to the outputs being achieved.
What should the project manager do to ensure that the intended value is being delivered at each phase?
CorrectIncorrect -
Question 95 of 175
95. Question
95. At daily collaboration meetings, several team members complain that they cannot concentrate due to a noisy work environment.
Who is responsible for solving this problem by creating a more conducive work environment?
CorrectIncorrect -
Question 96 of 175
96. Question
96. A major change in a government policy may cause a project’s completion date to be delayed. The project is 90% complete.
What should the project manager do next?
CorrectIncorrect -
Question 97 of 175
97. Question
97. A project is close to completion when an unidentified and influential stakeholder appears and threatens to put the project in jeopardy by not approving the closing documents.
Which two actions should the project manager have done to avoid this? (Choose two)
CorrectIncorrect -
Question 98 of 175
98. Question
98. Organizations face different challenges within their operational areas due to external factors. This has required companies to develop formal engagement documents to guide their various operations.
How should a project manager make their team members and stakeholders aware of the uniqueness of the organizational standards?
CorrectIncorrect -
Question 99 of 175
99. Question
99. On an agile project, a team member raises concerns about health and safety issues related to the project deliverable. How should the project manager handle health and safety issues on projects?
CorrectIncorrect -
Question 100 of 175
100. Question
100. Close to the end of a large project, some of the technical reports related to the delivered service were not ready. The project manager asked the team members for the missing documents, but the team claimed they had already fulfilled their assigned tasks.
How should the project manager address this concern?
CorrectIncorrect -
Question 101 of 175
101. Question
101. An agile project team is struggling to keep track of the changes being applied to the product, because its process is cumbersome and error-prone. What should the project manager do to address the issue?
CorrectIncorrect -
Question 102 of 175
102. Question
102. A team member is unable to work for one week because of sick leave. The team member is currently assigned to a task on the critical path.
What is the next step the project manager should take?
CorrectIncorrect -
Question 103 of 175
103. Question
103. A team member is unhappy with their workload and feels they are not being supported enough. The project manager wants to meet with the team member to discuss their concerns and apply a compromise/reconcile conflict management approach.
What should the project manager do first?
CorrectIncorrect -
Question 104 of 175
104. Question
104. During a Scrum board review for a hybrid project, a team member suggests adding a task that is outside of the baseline scope. This task could reduce risk to the project. The team member raises it in the review.
What should the project manager do?
CorrectIncorrect -
Question 105 of 175
105. Question
105. There are concerns that a scheduled-for-release product may not meet the agreed-upon end user requirements. How should a project manager avoid this situation in the future?
CorrectIncorrect -
Question 106 of 175
106. Question
106. A hybrid project involving many stakeholders is underway. As requested by the project management office (PMO), the project status reports, as well as other project documents, are being stored in a central repository. When reviewing the documents stored in the repository, the project manager discovered that documents were either not updated or were missing.
What should the project manager do in this situation?
CorrectIncorrect -
Question 107 of 175
107. Question
107. A project manager works in an organization using a hybrid project delivery approach. The scope of the project is to implement a new human resources system. The infrastructure will be delivered by another project, and both projects are part of a business transformation program aimed to improve human resources processes. The project schedule needs to be finalized, but the project manager of the other project is unable to provide delivery dates for the infrastructure.
What should the project manager do?
CorrectIncorrect -
Question 108 of 175
108. Question
108. A project manager is in the initiation phase of a new project and is preparing to develop a project team charter. The project team consists of members from different departments within the organization, and collaboration is vital for project success. What should the project manager do to create an effective project team charter?
CorrectIncorrect -
Question 109 of 175
109. Question
109. A project advisory team is working remotely from the core project team. There is a constant flow of information between these two teams, and both teams approve project documents. Any delays in approvals will result in additional expense.
Which practice would assure the project manager that all of the documents are on hand, updated, and approved properly?
CorrectIncorrect -
Question 110 of 175
110. Question
110. During a predictive project, the project manager is in the process of finalizing the exit criteria for a significant system development project. At this stage, a stakeholder responsible for risk and compliance informs the project manager that an additional deliverable must be completed due to recently passed legislation by the local government. This requested change is expected to have an impact on the scheduled release date of the project.
What should the project manager do?
CorrectIncorrect -
Question 111 of 175
111. Question
111. At a review meeting, the project manager learns about unclear requirements that may impact the project’s scheduled completion. The project sponsor still wants to meet the original deadline.
How should the project manager approach the issue using agile practices?
CorrectIncorrect -
Question 112 of 175
112. Question
112. An agile project team member is working on a user story that is overdue. This delay is causing the team to miss sprint goals for a specific functionality. The reasons for this delay are unknown to the project manager.
What should be project manager do first?
CorrectIncorrect -
Question 113 of 175
113. Question
113. As a project is nearing completion, a struggle between the product owner and the project sponsor regarding who owns the benefits derived from the deliverable becomes a matter of litigation.
What should the project manager have done to prevent this conflict from occurring?
CorrectIncorrect -
Question 114 of 175
114. Question
114. In an agile project initiation phase, a senior team member suggests using a new documentation tool based on experience on a previous project.
What should the project manager do first?
CorrectIncorrect -
Question 115 of 175
115. Question
115. A company must launch a global product to respond to a competition threat. As part of an agile approach, the team chooses Region X as the baseline to test the first iteration. While the product meets standards and requirements in Region X, it does not comply with two of the other regions’ standards.
What should the project manager do?
CorrectIncorrect -
Question 116 of 175
116. Question
116. A company is transitioning from using a predictive approach to a hybrid predictive-agile project implementation. The leadership team is concerned about benefits realization and is closely following up on one of the project iterations with the project manager.
What should the project manager do in this situation?
CorrectIncorrect -
Question 117 of 175
117. Question
117. A company is developing a new product that needs to implement nonfunctional security requirements. The product owner is concerned about how the team can ensure the implementation of these nonfunctional requirements.
What should the project manager do?CorrectIncorrect -
Question 118 of 175
118. Question
118. During a one-on-one session, a new team member shared their frustration regarding their inability to successfully complete an assigned task, even after the team member put forth their best effort.
What should the project manager do first to address the team member’s concerns?
CorrectIncorrect -
Question 119 of 175
119. Question
119. A project manager has completed the project deliverable and has passed the acceptance criteria. Which statement confirms that project benefits have been achieved?
CorrectIncorrect -
Question 120 of 175
120. Question
120. A team member in a hybrid organization informs the project manager of a new way to execute an activity with a shorter duration. The project manager has not used the new process before, but a trusted team member explains that their previous experience with the process validates the efficacy of the new process. Which two actions should the project manager take? (Choose two).
CorrectIncorrect -
Question 121 of 175
121. Question
121. A two-year project was awarded to a company six months ago, but the procurement process has not yet been initiated. What should the project manager do to get the project moving forward?
CorrectIncorrect -
Question 122 of 175
122. Question
122. A project manager has just finished a project charter and received approval from the project sponsor. The project manager then presented the project charter to the stakeholders and noticed a lack of participation from some of them during this meeting.
What should the project manager do?
CorrectIncorrect -
Question 123 of 175
123. Question
123. Even though the customer is receiving sprint velocity and results reports from the project manager by email, escalations to the project sponsor complaining about project performance are common. What should the project manager do in this situation?
CorrectIncorrect -
Question 124 of 175
124. Question
124. At the beginning of a project, a stakeholder is concerned that the initiative may not deliver value to the organization. What should the project manager do first to increase the chances of project success?
CorrectIncorrect -
Question 125 of 175
125. Question
125. In order to determine a new hybrid approach for a project, the project manager decides that an assessment of the organizational culture is needed.
The project manager should consider a balance between which two elements?
CorrectIncorrect -
Question 126 of 175
126. Question
126. A company has launched a new strategic project. The goal and scope of the project were loosely defined at the executive committee meeting, and the stakeholders have been appointed. The project manager needs to hold the kickoff meeting. However, most of the stakeholders are in different locations and some are on vacation.
What should the project manager do?
CorrectIncorrect -
Question 127 of 175
127. Question
127. A project manager is managing a project using an agile approach. The project is nearing its final stages, and the team is reviewing the project deliverables. During this review, it becomes evident that a crucial feature is missing from the project’s artifacts. This feature is necessary for the system to comply with a new government regulation.
How should the project manager resolve this issue?
CorrectIncorrect -
Question 128 of 175
128. Question
128. During a retrospective meeting, project team members complain that open issues that were not fixed during the iteration are impacting their velocity. What should the project manager do to improve productivity?
CorrectIncorrect -
Question 129 of 175
129. Question
129. A client’s interactions with the project team have been somewhat negative. Project team members don’t want to be part of the project any longer.
What should the project manager do?CorrectIncorrect -
Question 130 of 175
130. Question
130. A key stakeholder is upset about the new features in the current iteration for the product. The key stakeholder was unavailable during the last review and did not have the opportunity to provide input.
What should the project manager have done to prevent the stakeholder from being upset?
CorrectIncorrect -
Question 131 of 175
131. Question
131. A project manager receives an email shortly after the beginning of a sprint. It is from a key stakeholder who is unfamiliar with agile methodologies and has a serious complaint about the work that was just started. The stakeholder insists that one deliverable should be changed. What should the project manager do?
CorrectIncorrect -
Question 132 of 175
132. Question
132. During a project team meeting, team members have identified a list of risks that may occur during the project. The project sponsor would like to meet with the project manager to evaluate the importance of each risk. What type of analysis should the project manager perform in preparation for a meeting with the sponsor?
CorrectIncorrect -
Question 133 of 175
133. Question
133. An agile project was scaled from the feasibility study phase to the implementation phase. Due to time constraints, the same team is assigned to the project, except for one team member who was replaced with a new team member. Many of the team members do not get along with the new team member and are unwilling to work in the next phase.
How should the project manager ensure that the team is ready for the next phase?
CorrectIncorrect -
Question 134 of 175
134. Question
134. A team is working on a new technology deployment project. This product has never been implemented before so there is no past data or historical records. The team is challenged to provide an initial timeline, budget, and other critical estimations to the client.
How should the project manager handle this situation?CorrectIncorrect -
Question 135 of 175
135. Question
135. An agile project to implement a new automation process in a factory is underway. The project manager needs a vendor to help with the installation.
What should the project manager do before the vendor comes to work with the team?
CorrectIncorrect -
Question 136 of 175
136. Question
136. An agile project is midway through its ten iteration cycles. During the last iteration, the team had to work overtime to accomplish the goal. In the iteration retrospective, the team agreed that they took more time than planned because they did not have the required experience when they executed the assigned tasks for the first time.
What should the project manager do?
CorrectIncorrect -
Question 137 of 175
137. Question
137. A new project manager joins an existing team. The project manager is made aware that there are strong personalities on the team, which has resulted in management becoming involved to resolve team performance issues.
What should the new project manager do when first joining this team?
CorrectIncorrect -
Question 138 of 175
138. Question
138. An organization using a predictive approach has decided to switch to an agile approach. The organization believes it will deliver more value to its customers and has decided that all projects will adopt the agile approach.
What should the project manager do to ensure benefits realization?
CorrectIncorrect -
Question 139 of 175
139. Question
139. In the middle of executing an IT project, two project team members discover a new feature that will change the appearance of the product and make it more aesthetically appealing. Excited about the opportunity to add this feature, they approach the project manager to approve this addition to the deliverables, which will increase client satisfaction and possibly increase the company’s chances of receiving additional project contracts from the client.
How should the project manager respond?
CorrectIncorrect -
Question 140 of 175
140. Question
140. A project manager has been assigned to a multimillion-dollar project already in execution. During a project status meeting, one of the team members mentions that there are some delays because a senior executive is not responding to communications.
What should the project manager do?
CorrectIncorrect -
Question 141 of 175
141. Question
141. A company is implementing a new computerized system. During project execution, the leader of a department that is critical to project completion raises a concern that the department’s requirements are completely missing from the approved project management plan. What should the project manager have done to avoid this issue?
CorrectIncorrect -
Question 142 of 175
142. Question
142. A project manager was assigned to deliver new software for university students. In this project, the software is being delivered to a specific niche of people. To better understand this niche, the project manager needs to develop an archetype user.
How should the project manager do that?
CorrectIncorrect -
Question 143 of 175
143. Question
143. A stakeholder is concerned that the project is falling behind schedule, based on unofficial information from the project team. Although some tasks have slipped, these tasks have free floats; otherwise, the project is on track. The project manager immediately contacted the stakeholder to show and explain the latest project status reports.
What should the project manager do next?
CorrectIncorrect -
Question 144 of 175
144. Question
144. The product owner has asked the project manager and the agile team to demonstrate the completed functionality to key project stakeholders. The project is in its early days and has only completed three iterations of functionality. This is the first time the stakeholders will be exposed to an agile project.
What should the project manager do?
CorrectIncorrect -
Question 145 of 175
145. Question
145. During the execution phase of a healthcare IT project, the customer’s project manager resigns and has not been replaced. The internal project manager finds out that, as a result, key stakeholders are no longer getting updated information in a timely manner.
What should the project manager do?CorrectIncorrect -
Question 146 of 175
146. Question
146. A team has recently adopted agile and is following a scrum model. There is a conflict between a lead developer and a quality assurance team member regarding their approaches, which is impacting the sprint goals.
What should the project manager do to resolve these conflicts?
CorrectIncorrect -
Question 147 of 175
147. Question
147. An entrepreneur has initiated a software development project. The project charter has been approved, and a project manager has been assigned to oversee the project’s execution. During development, unforeseen political risks arise, causing an urgent need to expedite the project. The project’s sponsor has requested a report on any anticipated delays.
Which tool should the project manager use to prepare the report on expected delays?
CorrectIncorrect -
Question 148 of 175
148. Question
148. A Scrum team noticed a trend of work spilling over for the last several sprints. The root cause of this has been identified as the code review task. This bottleneck appears to occur because the team is dependent on an external expert.
What should the project manager do first?
CorrectIncorrect -
Question 149 of 175
149. Question
149. A geographically distributed project team has development issues between the colocated and virtual teams, causing productivity to decrease.
What should the project manager do to address these issues?
CorrectIncorrect -
Question 150 of 175
150. Question
150. A project manager in Location A works with a local team, while developers are in another remote location, and a quality assessor is in yet another remote location. The project manager is aware that these distances mean that the team could struggle with lag when needing to communicate.
What could the project manager do to mitigate this issue?
CorrectIncorrect -
Question 151 of 175
151. Question
151. The project manager of a new hybrid project is trying to put together the project team. The best candidates for team members are geographically dispersed, so there is a risk that this situation will interfere with the performance of the project. Colocation would increase costs dramatically; and due to severe competition, the company is struggling financially to survive.
What should the project manager do?
CorrectIncorrect -
Question 152 of 175
152. Question
152. A project manager is working on an agile project that is currently in its third iteration. During the ongoing iteration, the customer contacts the project manager requesting additional features. These additional features are considered important and can be accommodated without requiring significant additional resources. The customer requests immediate changes to the current iteration to incorporate the additional features.
How should the project manager respond?
CorrectIncorrect -
Question 153 of 175
153. Question
153. During a steering committee meeting, a senior executive raised a concern that although the key cost parameters are reported to be on track, the project might not be delivering the work that was originally scheduled. What measurement should the project manager use to address this concern?
CorrectIncorrect -
Question 154 of 175
154. Question
154. A project was undertaken to set up a new business function in the company. Several months after completion, the project manager is still handling business operations for the project while working on another project.
What should the project manager have done at the beginning of the project to prevent this?
CorrectIncorrect -
Question 155 of 175
155. Question
155. Project team A is launching a complex program in collaboration with project teams B, C, and D. What should be the priority for project team A’s project manager during the early stages of the project?
CorrectIncorrect -
Question 156 of 175
156. Question
156. At what point in an agile project should a project manager engage stakeholders?
CorrectIncorrect -
Question 157 of 175
157. Question
157. A new product development project has been launched. The project sponsor has reviewed the results of the risk analysis as documented in the risk register and is confident the project will be successful. However, key investors are not as confident and want more information about the project and risks before investing.
What should the project manager do?
CorrectIncorrect -
Question 158 of 175
158. Question
158. An organization is trying to adopt agile approaches to execute projects for their customers. During project planning, the product owner proposed that any release to the customer should be approved by the legal department before it is shipped. The development team is disappointed as it may potentially delay releases and the delivery schedule.
Since other departments in the organization do not use agile, what should the project manager’s role be as a servant leader?
CorrectIncorrect -
Question 159 of 175
159. Question
159. A new solution is being deployed in several countries. Country A asked for a change in the solution in order to comply with its own customer market. The project manager for the deployment in country A accepted the change. When the project manager for the deployment in country B received the new version of the solution, the tests performed failed because this version is not consistent with country B’s regulations.
What should have been done to avoid this situation?
CorrectIncorrect -
Question 160 of 175
160. Question
160. A functional manager involved in a project complains about the latest quality metrics reports associated with all previous iterations. The team does not think this is a valid complaint.
What should the project manager do first?
CorrectIncorrect -
Question 161 of 175
161. Question
161. A project manager is working in the fifth month of an implementation for a construction project. The planner reported that the current schedule performance index (SPI) and cost performance index (CPI) are 0.8 and 0.9, respectively.
Which two options will help to accelerate the project? (Choose two)
CorrectIncorrect -
Question 162 of 175
162. Question
162. A project manager is leading a project where a low-level stakeholder has just been promoted to a new position and has now become a high-level stakeholder. What should the project manager update to ensure the proper involvement of this stakeholder to the project?
CorrectIncorrect -
Question 163 of 175
163. Question
163. A newly appointed product owner is not sure how to prioritize product specifications and mentions this challenge to the project manager.
What should the project manager do to assist the product owner?
CorrectIncorrect -
Question 164 of 175
164. Question
164. A junior project manager approaches a senior project manager and asks for assistance in initiating the final closeout process for a project. Before offering guidance, the senior project manager requires additional information.
What should the senior project manager do first?CorrectIncorrect -
Question 165 of 175
165. Question
165. A member of the project team who was hired for six months to complete a specific task has decided to leave the project in the fifth month to pursue another job opportunity.
What should the project manager’s immediate action be?
CorrectIncorrect -
Question 166 of 175
166. Question
166. A project is following a strategic plan that includes key milestones that have been aligned with stakeholders. As the work is being executed, new tasks arise along with important dependencies that prevent the work from progressing as planned. The team is unable to determine who should make decisions and take action on the new tasks and dependencies.
What should the project manager do?
CorrectIncorrect -
Question 167 of 175
167. Question
167. A project manager has been assigned to lead a cross-functional project team. During a brainstorming session, the project manager realizes that some team members do not see the need for a change, and this is affecting the team’s output.
What should the project manager do?
CorrectIncorrect -
Question 168 of 175
168. Question
168. An innovative project is leveraging artificial intelligence (AI) to identify chemical compounds for the development of new products. The AI processing phase can vary in duration, ranging from three days to two weeks, and the outcomes are unpredictable. The project’s primary objective is to deliver at least one product specification within a fixed two-month timeframe while adhering to a strict budget that cannot be increased.
What action should the project manager take to optimize the use of the fixed budget and deliver the highest possible business value?
CorrectIncorrect -
Question 169 of 175
169. Question
169.In a multidisciplinary project, a project manager is delegating some project management activities to several team members.
What should the project manager do first?
CorrectIncorrect -
Question 170 of 175
170. Question
170. A project manager has created the stakeholder list and is deciding how to distribute information effectively to the customer. What should the project manager do next?
CorrectIncorrect -
Question 171 of 175
171. Question
171. A project manager leads a project team on a project. This project’s goal is to enhance a product’s capability in the market.
What should be the top consideration when defining the team’s key performance indicators (KPIs)?
CorrectIncorrect -
Question 172 of 175
172. Question
172. A project manager is managing a long-term project that is behind schedule. The client is concerned that the project will be delayed.
Which two actions should the project manager take to address the client’s concerns? (Choose two)
CorrectIncorrect -
Question 173 of 175
173. Question
173. A country implements new labor laws with specific requirements for labor health and safety. The company’s existing procedures haven’t been updated yet, but management informed all project managers of the regulations.
What should the project managers do first?
CorrectIncorrect -
Question 174 of 175
174. Question
174. A project is nearing completion and a stakeholder wants to know how the project outcomes will impact the organization. What should the project manager review with the stakeholder?
CorrectIncorrect -
Question 175 of 175
175. Question
175. Early in a project, the project manager realizes that one of the key team members is not prepared to perform the assigned task.
How should the project manager address this issue?
CorrectIncorrect